ASMETECH has been awarded complete Engineering and Design work by E&C Projects Pvt. Ltd for HGP Dust Treatment Plant of "Hindustan Zinc Limited", Chanderiya:-

ASMETECH has received its first major order include complete design and engineering in Civil, Mechanical and Piping job. This project would require about 1500 effort hours. It is a fast track revamp job, to be completed by mid-January 2013.
Already considerable progress has been made. Following is the list of major activity :-

  • A. Complete design and drawing of Storage tank. .
  • B. Civil foundation design & drawings of Pumps, Tank, Filter press and other equipment.
  • C. Steel Platform Design and drawing.
  • D. Piping & Pipe support location and detail.
  • E. Pipe routing and layout
  • F. Piping Isometric.
 